Bali is known for its coastline, but its east coast is now at the center of a dispute over energy. Customary leaders in Serangan village say a planned floating liquefied natural gas terminal would sit too close to their sacred waters and fishing routes. Indonesia’s environment ministry issued an environmental permit for the project earlier this year, and the dispute has grown as the terminal’s location and approval have come under closer scrutiny. The story is a useful test of how the island meets rising power demand while protecting the communities that live along its shore ([1]).
A distance measured in kilometers and in fishing routes
The central point of disagreement is distance. At a meeting on November 14, I Nyoman Gede Pariartha, the traditional leader in Serangan, rejected a planned separation of 3.5 kilometers, or about 2.2 miles, from the village. He argued that the vessel is large and sits very close to the village’s sacred point and to the routes its fishers use.
For the community, the concern is practical as well as cultural. Small-scale fishers depend on the nearby sea, and customary leaders say a facility of this size could limit the area they can safely work. Environmental groups have made a similar argument. Greenpeace Indonesia’s Yuyun Harmono warned that LNG facilities in southern Bali could shrink fishing grounds, damage mangroves and harm sea turtle habitat, according to the original report.
How the floating terminal would work
The planned Floating Storage and Regasification Unit would receive liquefied natural gas from tankers offshore. It would then convert the fuel back into natural gas and send it by pipeline to the Pesanggaran power station, a 200 megawatt gas-fired plant beside a protected mangrove forest on the northern fringe of Benoa Bay ([1]).
Planners say the facility would make Bali’s power supply more dependable. The island has a population of about 4.5 million, yet it received almost 7 million tourism visits in 2025, and many visitors now stay for longer periods. Up to 30 percent of Bali’s electricity currently arrives through cables from Java. Greenpeace has noted that Bali has planned an addition of 1,550 megawatts of gas-fired capacity, with a floating unit of 145,000 cubic meters slated for Serangan ([2]).
The site has already changed once. The unit was previously planned for a location in Sidakarya village, and that proposal was moved after local opposition ([1]). The relocation shows how earlier objections have shaped the project, even though the current site still faces criticism.
Permit, protests and the political response
Bali’s governor, Wayan Koster, has said the project will go ahead despite objections from some customary communities. Local reporting describes his position as a push for energy self-sufficiency, and it frames the terminal as a way to reduce the island’s reliance on electricity from Java ([3]).
Pressure has also reached Jakarta. Members of the national House of Representatives’ Commission XII have said they will visit Serangan to review the concerns raised by village residents, which signals that the dispute has moved beyond village meetings ([4]). Greenpeace Indonesia has staged protests as well, including a banner reading “No Fossil Gas in Paradise” displayed in front of a floating unit at Benoa ([2]).
What matters now
- The environmental permit has been issued, but local leaders still dispute the 3.5 km separation from their fishing grounds.
- The terminal is designed to receive LNG from tankers and supply gas-fired plants that serve Bali’s growing electricity demand.
- The site has already been moved once, and the national legislature has signaled further scrutiny.
The coming weeks will show whether the distance dispute leads to changes in the site or the project plan. For now, the debate pits Bali’s energy needs against the livelihoods and sacred places of the people who live on its coast, and the outcome will matter well beyond Serangan.